G7/h6 Fit Chart (shaft-basis, clearance fit)

Precision sliding fit on the shaft-basis system, equivalent to H7/g6. Use G7 for the hole when the shaft is a standard part (h6 ground shafting, dowel pins).

Deviations of hole G7 and shaft h6, and the resulting maximum / minimum clearance (negative values mean interference). Nominal sizes 0–500 mm, values in mm.

Nominal size (mm)Hole G7 (upper / lower)Shaft h6 (upper / lower)Max. clearanceMin. clearanceFit type
0 ~ 3+0.012 / +0.0020 / -0.006clearance 0.018clearance 0.002Clearance
>3 ~ 6+0.016 / +0.0040 / -0.008clearance 0.024clearance 0.004Clearance
>6 ~ 10+0.020 / +0.0050 / -0.009clearance 0.029clearance 0.005Clearance
>10 ~ 18+0.024 / +0.0060 / -0.011clearance 0.035clearance 0.006Clearance
>18 ~ 30+0.028 / +0.0070 / -0.013clearance 0.041clearance 0.007Clearance
>30 ~ 50+0.034 / +0.0090 / -0.016clearance 0.050clearance 0.009Clearance
>50 ~ 80+0.040 / +0.0100 / -0.019clearance 0.059clearance 0.010Clearance
>80 ~ 120+0.047 / +0.0120 / -0.022clearance 0.069clearance 0.012Clearance
>120 ~ 180+0.054 / +0.0140 / -0.025clearance 0.079clearance 0.014Clearance
>180 ~ 250+0.061 / +0.0150 / -0.029clearance 0.090clearance 0.015Clearance
>250 ~ 315+0.069 / +0.0170 / -0.032clearance 0.101clearance 0.017Clearance
>315 ~ 400+0.075 / +0.0180 / -0.036clearance 0.111clearance 0.018Clearance
>400 ~ 500+0.083 / +0.0200 / -0.040clearance 0.123clearance 0.020Clearance

Max. clearance = hole upper deviation − shaft lower deviation; min. clearance = hole lower deviation − shaft upper deviation; a negative result is an interference. Each row applies to the whole size range shown.

What is the shaft-basis system?

The shaft is the datum (h, upper deviation 0) and different fits are obtained by changing the hole tolerance. Used when the shaft is a ready-made part such as ground shafting or a dowel pin, or when several different fits are needed along one shaft.

Other common fits

FAQ

Is G7/h6 a loose fit or a tight fit?

It is a clearance fit (shaft-basis system). Precision sliding fit on the shaft-basis system, equivalent to H7/g6. Use G7 for the hole when the shaft is a standard part (h6 ground shafting, dowel pins).

How much clearance does G7/h6 give at Ø10?

The G7 hole is made to 10(+0.020/+0.005) and the h6 shaft to 10(0/-0.009). At the loosest that gives clearance 0.029, at the tightest clearance 0.005 (mm).

Can I use a stock dowel pin as the shaft?

Stock dowel pins come in h6, h7, m6 (plus tolerance) and minus tolerance (0/-0.02). Put the hole tolerance (G7) and the application in your enquiry and we will tell you which one fits as it is.

Tell us the tolerance on your drawing and we will match it to stock. Write the size as 8(0/-0.015) or 8h7 and e-mail it with material, length and quantity to sfp@sfp-tw.com, or check availability directly in the online catalog. Stock dowel pins come in h6 / h7 / m6 as well as minus and plus tolerance; whenever the tolerance zone of a stock part lies entirely within the acceptance range on your drawing, it can ship straight away with no wait for custom production.

Values follow ISO 286-1; the table was cross-checked cell by cell against three independent sources on 2026-08-26 (6,674 cells agree, 0 errors). Coverage: shafts a–z and the corresponding uppercase holes, IT1–IT13, nominal sizes 0–500 mm. cd/ef/fg/za/zb/zc, sizes above 500 mm and grades above IT13 are not included: the tool reports "not found" and never extrapolates. Data sources and verification →

🔍 Open the online catalog🧮 Tolerance calculator